If 25 workers take 30 days to complete a task, what is the equivalent working time in days for 40 workers?

Study for the ABSA 4th Class Power Engineer Test. Explore questions with hints and explanations. Get ready to ace the exam!

To determine the equivalent working time for 40 workers given that 25 workers complete a task in 30 days, we can use the concept of worker-days, which is the product of the number of workers and the number of days they work.

First, calculate the total amount of work done in terms of worker-days by the original group:

25 workers × 30 days = 750 worker-days.

Now, if we have 40 workers, we need to find out how many days they would need to complete the same amount of work:

Let ( x ) be the number of days required for 40 workers to do the same amount of work. Therefore, we can set up the following equation:

40 workers × ( x ) days = 750 worker-days.

To find ( x ), we rearrange the equation:

( x = \frac{750}{40} ).

When we calculate this, we find:

( x = 18.75 ).

Since we are typically interested in whole days, we would round up to the nearest whole day, resulting in 19 days. However, to match the choices provided and find a closer logical understanding, we can verify other calculations.

Given the rates of work, if 25